Q:

If 80 Persons can finish a work in 16 days by working 6 hours a day, the number of hours a day should 64 persons work to finish that same job in 15 days is:

  • 1
    5 hours
  • 2
    7 hours
  • 3
    8 hours
  • 4
    6 hours
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "8 hours"