Join Examsbook
520 0

Q:

B is 20% more efficient than A. A started the work and work for x days and then A is replaced by B. B completed the remaining work in x+8 days. Ratio of the work done by A and B is 2:3. In how many days A and B working together can complete the whole work?

  • 1
    $$36{7\over11}$$
  • 2
    35
  • 3
    $$36{4\over11}$$
  • 4
    None of these
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " $$36{4\over11}$$ "

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully