Join Examsbook
864 0

Q:

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one- third of the road in made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

  • 1
    100
  • 2
    60
  • 3
    50
  • 4
    75
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "75"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully