A contract is to be completed in 50 days and 105 men were set to work, each working 8 hour a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 hour a day?

  • 1
    34
  • 2
    36
  • 3
    35
  • 4
    37
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "35"