Q: The ratio of number of students taking admission in a organisation X and Y was 5:8. If 20% of students exceed in organisation X and 10% of students exceed in organisation Y, then new ratio of students is 3732 15d1b13e08a754124194a7564
5d1b13e08a754124194a7564- 115:22true
- 215:16false
- 35:4false
- 45:7false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "15:22"
Q: 240 metre long train running at 48 km/hour cross a platform in 39 seconds. What is the length of platform? 3369 05d198ffd1388cd24f08602fd
5d198ffd1388cd24f08602fd- 1520false
- 2280true
- 3480false
- 4270false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "280"
Q: A cycle is sold for Rs.2070 at profit of 15%, at what profit of 15%, at what price it should be sold so as to earn 25% Profit. 3337 05d13299509a40f38019e53a2
5d13299509a40f38019e53a2- 12150false
- 22250true
- 32350false
- 42450false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "2250"
Q: A person sells two objects in Rs 5000 each. He sells one for 20% profit and another for 20% loss. Find his total profit or loss percent in the whole transaction. 3220 05d13414c40daee3c552fcb44
5d13414c40daee3c552fcb44- 14 % profitfalse
- 24% Losstrue
- 320% Profitfalse
- 4No Profit and Lossfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "4% Loss"
Q: A single person takes 4 minutes to type a page, if from 12 noon to 1.00 pm., 1080 pages are to be typed, how many persons should be employed on this job? 3104 05d148d649aeb0a08f1e67464
5d148d649aeb0a08f1e67464- 1108false
- 260false
- 390false
- 472true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "72"
Q: Ramesh and Dinesh can complete a work in 15 and 20 days respectively. Ramesh started working but after 5 days Dinesh replaced Ramesh. Find the share of Dinesh in Rs 15000 2963 05d1491b097a68b089a7aa717
5d1491b097a68b089a7aa717- 1Rs 5000false
- 2Rs 9000false
- 3Rs 10000true
- 4Rs 8000false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "Rs 10000"
Q: 30 Men contracts to complete a work in 50 days. But after 25 days, it is come to know that only 1/3rd of the work has been done. How many more workers are required to complete the work in time? 2913 25d149b7e97a68b089a7aa859
5d149b7e97a68b089a7aa859- 125false
- 230true
- 335false
- 440false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "30"
Q: Ratan can complete a work in \(5 {1 \over 2}\) days while Rupesh can complete it in \(10 {1 \over 2}\) days. In how many days can they both complete it working on it together? 2872 25d147c239aeb0a08f1e67215
5d147c239aeb0a08f1e67215- 1\(3 {39 \over 64 }\)true
- 2\(4 {39 \over 64 }\)false
- 3\(5 {39 \over 64 }\)false
- 4\(6 {39 \over 64 }\)false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "\(3 {39 \over 64 }\) "
en632popular