A work is done in 16 days by 8 labours. They worked together for 2 days and after that 8 additional labours joined them. The rest work will be finished by them in ______

  • 1
    8 days
  • 2
    10 days
  • 3
    9 days
  • 4
    7 days
  • Show Answer
  • Workspace

Answer : 4. "7 days "