Get Started
282

Q:

40 men, working 8 hours a day can do a piece of work in 15 days. Find the number of days in which second group of 60 men working 4 hrs a day can do twice the work. Assume that 3 men of the first group do as much work in 2 hour as 4 men of the second group do in 3 hrs.

  • 1
    60 days
  • 2
    40 days
  • 3
    80 days
  • 4
    70 days
  • 5
    75 days
  • Show Answer
  • Workspace

Answer : 3. "80 days"

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today