Q: An industrial loom weaves 1.14 meters of cloth every second. Approximately, how much time will it take to weave 52 meters of cloth ? 2143 1

  • 1
    29.32 sec
    Correct
    Wrong
  • 2
    42.51 sec
    Correct
    Wrong
  • 3
    39.25 sec
    Correct
    Wrong
  • 4
    45.61 sec
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "45.61 sec"
Explanation :

Answer: D) 45.61 sec Explanation: Given loom weaves 1.14 mts of cloth in one second then 52 mts of cloth can be weaved by loom in, 1.14 ----- 1 52.0 ------?  ⇒521.14= 45.61 sec

Q: Shyam can work at thrice the speed than Naresh. If together they can complete a work in 32 days, in how many days can Naresh alone complete it? 2114 0

  • 1
    120
    Correct
    Wrong
  • 2
    128
    Correct
    Wrong
  • 3
    124
    Correct
    Wrong
  • 4
    144
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "128"

Q: Ram and Naresh can complete a work in 20 days while Naresh takes 36 days. They get Rs 720 for it. Find salary of Ram. 2075 2

  • 1
    Rs 300
    Correct
    Wrong
  • 2
    Rs 380
    Correct
    Wrong
  • 3
    Rs 400
    Correct
    Wrong
  • 4
    Rs 320
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Rs 320"

Q: A sum of Rs. 400 amounts to Rs. 480 in 4 years. What will it amount of if the rate of interact is increased by 2% ? 2065 0

  • 1
    Rs. 484
    Correct
    Wrong
  • 2
    Rs. 560
    Correct
    Wrong
  • 3
    Rs. 512
    Correct
    Wrong
  • 4
    None of these
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Rs. 512"

Q: A bus is running at 60 kmph without any stoppage. But, with stoppages its average speed is 50 kmph. Find the time of stoppage by bus per hour. 2064 0

  • 1
    15 minutes/hour
    Correct
    Wrong
  • 2
    20 minutes/hour
    Correct
    Wrong
  • 3
    12 minutes/hour
    Correct
    Wrong
  • 4
    10 minutes/hour
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "10 minutes/hour"

Q: A certain work can be completed in 100 days by a certain number of men. But, due to the absence of 10 people it could be completed in 110 days. How many workers were employed initially? 2008 0

  • 1
    100
    Correct
    Wrong
  • 2
    110
    Correct
    Wrong
  • 3
    55
    Correct
    Wrong
  • 4
    50
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. " 110"

Q: Cost price of 21 objects is equal to selling price of 15 objects. What is the profit? 1972 0

  • 1
    25%
    Correct
    Wrong
  • 2
    30%
    Correct
    Wrong
  • 3
    33%
    Correct
    Wrong
  • 4
    40%
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "40%"

Q: A machine was sold at 10% Profit had it been sold for Rs 80 less the seller would have incurred 10% loss. What is cost price of Machine? 1968 2

  • 1
    350
    Correct
    Wrong
  • 2
    400
    Correct
    Wrong
  • 3
    450
    Correct
    Wrong
  • 4
    520
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "400"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully